[PM] The Progress of Bemis Subang Project

Bemis Subang is in Phase 2 as of 26th April 2017. This phase includes warehouse renovation, water tank installation and renovation in production zone. 
Water Tank installation is at 40% completion. The foundation slab progress is at 70% and the Water Tank Plinth Concreting has been completed. The remaining works are targeted to complete by the first week of July.

 